"This is one of the most exciting projects our City has undertaken," City Administrator Ford Handley told OBA in June. He was talking about a cluster of courts, pools and gyms that many Orange Beach households already reach by golf cart. The Recreation Campus on Wilson Boulevard is not new. It started in the 1990s with two tennis courts and some ballfields. The Tennis Center, Aquatics Center, Recreation Center and Community Center followed in the early 2000s, and the city added a gymnasium, a fitness center and a pickleball complex over the past six years.
According to the same report, the campus grew for decades without a unified design. City Engineer Chris Pappas has since drawn a master plan that treats the whole site as one place. The pickleball complex is already finished. The Aquatics Center expansion builds its new pool before it removes the old one, and a separate package of parking, tennis courts and a turf field is moving through design.
The Courts That Already Opened
The newest finished piece is the pickleball complex at 4869 Wilson Blvd. It has 14 lighted courts, shade cabanas, restrooms and a pavilion. The city's May 6, 2026 Town Hall presentation announced a ribbon-cutting for 10 a.m. on Thursday, May 7, and OBA reported in June that the complex had opened in May.
Those courts also brought parking with them. The campus had 360 parking spaces when the city presented its plan in May, and 98 of the spaces added under the master plan are tied to the pickleball project. Anyone who has circled the Tennis Center lot on a weekday evening can see why parking takes up so much of the master plan.
The Pool Plan Builds Beside the Old One
The Aquatics Center at 4853 Wilson Blvd. opened in May 2002. It has a heated 25-yard outdoor pool, a diving well, a tube slide and a seasonal children's wading pool, along with swim lessons and water aerobics. It is also home to the Orange Beach Swim Team. The city provides the pool space, certified lifeguards and coaches for practices, clinics and home meets, and children as young as 5 can start in the Junior Makos pre-team program.
On November 3, 2026, the City Council approved up to $274,000 for Lose of Tennessee, the firm that designed the expansion, to oversee construction of the first phase. OBA reported that the money pays for managing the work. It does not pay for building the new facilities. The project has moved in steps. The city hired Lose Design for initial planning in April 2025 and approved up to $781,700 for the design work in February 2026.
The sequence is what matters most for regular swimmers. Phase I adds a second, larger leisure pool, a new pump house with meeting rooms, and new pool decks. Its design-stage construction estimate is $7,240,375. Phase II then removes the existing pool, builds a replacement lap pool, and renovates the current pump house and pool house. That phase is estimated at $4,185,956. In June, OBA described the goal: expand the existing six-lane pool to eight lanes for high school and recreational swim teams, fitness swimmers, lessons and community programs, and add a recreational pool with an interactive splash pad for classes, open swim and family use. The construction will be phased "to keep the facility operational for the public."
Because the new pool goes in first, there is still water to swim in when the old pool comes out. Final construction costs, the building schedule and any effect on day-to-day operations had not been announced when the council voted.
The Timeline, in the City's Own Estimates
The cost estimate in the November 3 council packet assumes Phase I construction starts in April 2027. Baldwin Citizen reported that the start date is an assumption and has not been set. The firm's oversight proposal plans for a pre-construction meeting and 12 site visits over a nine-month Phase I build. Its letter puts Phase II at another nine months, and that phase will need its own oversight agreement.
The estimates also leave some costs out. They do not include design fees, furniture, equipment, audiovisual systems or any hazardous-material removal, and the council packet did not name a funding source for construction. If you are setting next year's lesson or swim-team calendar around the pool, use the April 2027 date and the two nine-month phases as the city's planning assumptions.
Parking, Tennis and a Turf Field Tie It Together
The rest of the master plan is a separate package that joins the buildings into one site. The concept adds four new tennis courts, an artificial-turf multipurpose field next to the Recreation Center, upgraded sidewalks and crosswalks, and dedicated golf-cart parking. In May, the Town Hall slides set a target to bid this package out by the end of 2026 and build it in 2027. That target covers the tennis, turf and parking work. The pool's own schedule comes from the later November estimate described above.
Parking shows the scale of the change. The proposal takes the campus from 360 spaces to 566, a net gain of 206. Besides the 98 spaces tied to pickleball, the plan adds 70 spaces on the west side and 30 along Wilson Boulevard, plus 8 from reworking an existing lot. It also lays out 58 golf-cart spaces, with the largest group at the Fitness Center and another 17 at the Tennis Center. Handley said the parking and circulation changes "will better accommodate golf carts, vehicles, school program participants, and users of the campus's many recreational facilities."
The turf field is meant for Expect Excellence, the city program based at the Recreation Center. It runs free after-school childcare, summer camp, athletics, and theatre and music. In the 2025-26 year, the city counted 458 children in after-school care, an average of 200 in summer camp, and 107 in the MAAD athletics program. A program that size explains why the field is planned right next to the Recreation Center.
Parks and Recreation Director Nicole Ard described the work in residents' terms. "Whether it's additional tennis courts, new recreational spaces, safer pedestrian access, or expanded parking, every improvement is designed to enhance the experience for our residents," she told OBA.
Contorno Park, the Quiet Edge of the Campus
In July 2024 the city bought Contorno Park, a 14-acre property beside the campus. The city's design for it centers on walking trails around a pond, picnic areas and open green space. The house on the property now holds the Parks and Recreation Department's administrative offices. The city calls it a passive park.
"As a passive park focused on walking, nature, and relaxation, it will provide residents with a beautiful new space to enjoy the outdoors while further connecting the Recreation Campus and surrounding areas," Ard told OBA. Handley called the new green space at Contorno Park a significant amenity for residents on the east side of town.
The Recreation Campus is one of several resident-focused projects the city has underway away from the beach, along with the living-shoreline work at Waterfront Park on Wolf Bay that we covered in Orange Beach's fall calendar post. For more on the city's neighborhoods, see our Orange Beach community page.
If your week includes laps at the Aquatics Center or a court time at 4869 Wilson Blvd., you already know what it's like to live near the campus. When you'd like to know what that location means for your own home's value, Shannon King Jha can walk you through it. Request Your Home Valuation to get started.